our-resource
Our Resource

NI 43-101

An NI 43-101 compliant technical report was prepared by Foster Wheeler and ERCOSPLAN Ingenieurgesellschaft Geotechnik und Bergbau mbH, effective October 21, 2011. A summary of the Mineral Reserves of the Karnalyte Property identified in the report is as follows: 


Proven Reserves

Mineralized Material (million tonnes)

Average KCl Grade    (% KCl)

Mineable KCl Tonnage (million tonnes)

Total Average Carnallitite

261.6

18.7

49.0

Total Average Sylvinite

 52.7

26.3

13.9

Total

314.3

 

62.9

 

Probable Reserves

Mineralized Material (million tonnes)

Average KCl Grade   (% KCl)

Mineable KCl Tonnage (million tonnes)

Total Average Carnallitite

416.0

18.5

77.0

Total Average Sylvinite

 58.3

25.8

15.0

Total

474.3

 

92.0











The 43-101 complaint report states that 144 million tonnes of potash product can be extracted and produced from the Project's reserves at 97% KCl and 90% plant efficiency, which suggests a project life of 68 years at a production rate of 2.125 million tonnes per year.

A complete copy of the 43-101 is available at www.sedar.com.